A Global Utility Contracted 33 Deliverables. Then Asked for 37 More.

Enterprise Asset Management IFS EAM and Supply Chain One of the largest utility companies in the world
  • {{ s.stat }}

    {{ s.label }}

The Situation

One of the largest utility companies in the world keeps power flowing to millions of customers. Some of them are hospitals. Nobody gets to schedule an outage around a maintenance backlog.

The company was built from utilities acquired over many years. Each arrived with its own software, and where two of them happened to run the same product, they ran it differently. The same class of asset carried different names, different categories, and different maintenance practices depending on which predecessor utility had owned it.

AS8, the core work management and supply chain platform, had gone out of support and needed phasing out, which set the clock on all of it.

So the implementation was never really about replacing a system. It was about standardizing products, data, and processes across the whole enterprise, so the organization could make proper use of the data it already held, without making the daily job worse for the people doing it.

The Approach

Tsunami joined an implementation that had already been running for a year.

Walking in a year late is awkward. The decisions have been made, the momentum belongs to someone else, and a new party either spends six months getting oriented or starts contributing immediately. Tsunami's first contribution was to work out where the program actually stood, then write it down.

The assessment set out foundational requirements the program hadn't yet established. Every large implementation accumulates them: decisions get made under time pressure, the work moves on, and nobody goes back to check what was assumed rather than settled. Putting that on paper is difficult from inside a program and straightforward from beside one.

From there, Tsunami took a lead role across four work streams:

  1. {{ p.n }}

    {{ p.title }}

    {{ p.body }}

Alongside the project work, Tsunami provides daily and weekly production support across several product areas, and collaborates directly with the other vendors and business units involved in the program.

The Results

33

deliverables contracted

37

more added on top, every one by purchase order

Work streamContractedAdded
{{ w.name }}{{ w.contracted }}+{{ w.added }}
{{ r.lead }}
{{ r.body }}
Talk to Our Asset Management Team →

Why This Team

Tsunami fields the most experienced IFS Asset Management team in North America, backed by more than 100 years of collective IFS experience and over 50 years in IFS EAM and service management alone. That depth gives the client an independent read on what the platform will and won't do, which matters when you are deciding whether to configure around a limitation or redesign a process to fit it.

Half of Tsunami's people spent 15 to 20 years in operations leadership before joining, in asset-intensive environments where the maintenance backlog was theirs to answer for. On a program like this one, that shows up as somebody saying the requirement you just wrote will not survive contact with a crew at 6am, before it gets built.

The Relationship

The program is still early, and Tsunami continues to lead its four work streams and provide daily and weekly production support, working alongside the client's other vendors and business units.

Where it's heading is already clear. The client has asked Tsunami to extend the work, and further proposals are with them now.

Already Mid-Program and Not Sure What You're Standing On?

The hardest engagements to join are the ones already moving. If yours is, we'll tell you where it actually stands before we tell you what we'd do about it.

Speak to an Expert

A Global Utility Contracted 33 Deliverables. Then Asked for 37 More.

Enterprise Asset Management IFS EAM and Supply Chain One of the largest utility companies in the world
  • >50%

    of Scope Added After Kickoff

  • 4

    Work Streams Led

  • 2027

    Phased Rollout Into

  • 100+

    Years Collective IFS Experience

  • 1 Year

    Into an Active Program at Joining

The Situation

One of the largest utility companies in the world keeps power flowing to millions of customers. Some of them are hospitals. Nobody gets to schedule an outage around a maintenance backlog.

The company was built from utilities acquired over many years. Each arrived with its own software, and where two of them happened to run the same product, they ran it differently. The same class of asset carried different names, different categories, and different maintenance practices depending on which predecessor utility had owned it.

AS8, the core work management and supply chain platform, had gone out of support and needed phasing out, which set the clock on all of it.

So the implementation was never really about replacing a system. It was about standardizing products, data, and processes across the whole enterprise, so the organization could make proper use of the data it already held, without making the daily job worse for the people doing it.

The Approach

Tsunami joined an implementation that had already been running for a year.

Walking in a year late is awkward. The decisions have been made, the momentum belongs to someone else, and a new party either spends six months getting oriented or starts contributing immediately. Tsunami's first contribution was to work out where the program actually stood, then write it down.

The assessment set out foundational requirements the program hadn't yet established. Every large implementation accumulates them: decisions get made under time pressure, the work moves on, and nobody goes back to check what was assumed rather than settled. Putting that on paper is difficult from inside a program and straightforward from beside one.

From there, Tsunami took a lead role across four work streams:

  1. 01

    Data migration

    Reconciling asset data from utilities that had each named, categorized, and maintained the same equipment differently.

  2. 02

    Supply chain

    Implementing IFS Supply Chain alongside EAM, rather than treating materials as an afterthought to asset management.

  3. 03

    Finance

    Integration to the general ledger they already run, which the program didn't control and couldn't disrupt.

  4. 04

    Training

    Preparing the people who have to use the system every day, which is where a standard either takes hold or quietly gets worked around.

Alongside the project work, Tsunami provides daily and weekly production support across several product areas, and collaborates directly with the other vendors and business units involved in the program.

The Results

33

deliverables contracted

37

more added on top, every one by purchase order

Work streamContractedAdded
Work management4+10
Finance1+4
Supply chain11+12
Foundational configuration11+7
The program hasn't gone live.
On a phased enterprise rollout running into 2027, most of the outcomes an operator would care about aren't measurable yet, and a story claiming otherwise wouldn't be worth reading. What can be measured is what the client has done with the relationship.
More than half the scope was requested after the work started.
33 deliverables contracted. 37 more added on top. Every one of those additions took a purchase order. The additions landed in the hardest areas: work management, finance, supply chain, and foundational configuration between them absorbed all but four of the additions, and they are exactly where a client with doubts pulls back first.
A rollout sequenced into 2027.
Nine phases: warehouse management, preventive maintenance, corrective maintenance, supply, supplier relationship management, supplier information management, inventory, procurement, and accounts payable. Each lands on its own schedule, which is how an enterprise this size keeps the lights on while it changes the system that runs them.
Talk to Our Asset Management Team →

Why This Team

Tsunami fields the most experienced IFS Asset Management team in North America, backed by more than 100 years of collective IFS experience and over 50 years in IFS EAM and service management alone. That depth gives the client an independent read on what the platform will and won't do, which matters when you are deciding whether to configure around a limitation or redesign a process to fit it.

Half of Tsunami's people spent 15 to 20 years in operations leadership before joining, in asset-intensive environments where the maintenance backlog was theirs to answer for. On a program like this one, that shows up as somebody saying the requirement you just wrote will not survive contact with a crew at 6am, before it gets built.

The Relationship

The program is still early, and Tsunami continues to lead its four work streams and provide daily and weekly production support, working alongside the client's other vendors and business units.

Where it's heading is already clear. The client has asked Tsunami to extend the work, and further proposals are with them now.

Already Mid-Program and Not Sure What You're Standing On?